Project overview
The project delivered the electrical power distribution works for the resort, centered on Automatic Transfer Switch (ATS) panels and the feeder cables that supply them. Work was carried out in the panel room and at the outdoor transformer area. Scope of Work: 1. ATS Panel Works (fabrication and installation) - Panel installation, busbar and MCCB mounting - Control wiring, indicator lamps, and metering 2. Feeder Cable Installation - Trench excavation and cable routing - Cable cutting, copper lugging, and termination - Phase identification and earthing connections 3. Dismantling and Tidying of Existing Infrastructure - Removal of old or unused cables and components - Reorganizing cable trays and bundling remaining cables 4. Testing and Commissioning - Termination and visual checks - Voltage and frequency verification - Energizing and functional testing Safety: All personnel used complete PPE (helmets, safety vests, gloves, safety boots) in line with the site PPE signage.